Which pipes need heat trace in Central Texas, and should it be self-regulating or constant wattage?
Heat-trace any outdoor or rooftop water line that can sit still in a freeze, starting with small lines, dead legs, valves, risers and pumps. For building and plant piping here, self-regulating cable under the insulation with an ambient thermostat is the usual choice, and constant wattage is kept for long, uniform runs where an engineer designs the circuit and its controller.
Central Texas does not freeze often, so most buildings and plants here are not designed around it. When it does freeze it can stay below freezing for days, as it did in February 2021 during Winter Storm Uri. The lines that break are rarely the big ones in a heated room. They are the small, still, exposed ones on a roof or in a yard.
This year our crews traced rooftop chilled-water piping in Austin, priced heat trace on process equipment near Brenham, and finished freeze protection on package water plants. This is the short list we use to decide what gets traced, and how we build it.
What freezes first
Water that moves rarely freezes. Water that sits still does. On a typical commercial roof or plant yard, these go first:
- Small lines, 2 inch and under. Make-up water, wash water and instrument lines hold little heat and lose it fast.
- Dead legs and idle branches. Bypass lines, standby pumps and branches that run only a few times a year sit full of still water.
- Valves, flanges and pumps. They have far more exposed metal than straight pipe, and they are the hardest part to insulate tightly.
- Risers and roof runs. Where a line leaves the building it meets wind, and a rooftop line has nothing sheltering it.
- Chilled-water piping on the roof. In winter the chiller may be off, and a full chilled-water line on a roof is still water in the wind.
Equipment can need it too. One bid this year was heat trace on the steel structure and auger cylinders of a water-screening unit, not on pipe at all.
Not every outdoor line needs trace. On one chiller-plant job the drawings traced the chilled and heating water lines to a new rooftop unit, but called for the condensate line to be insulated and jacketed only. Horizontal roof drains usually get insulation against condensation rather than heat trace, while sanitary lines in a crawl space can need both the cable and insulated traps. Read the drawings line by line rather than tracing everything that is outside.
Self-regulating or constant wattage
Both are electric cables that run along the pipe under the insulation. The difference is how they behave as the pipe warms.
Self-regulating cable puts out more heat when the pipe is cold and less as it warms. It can be cut to length on site, and it can cross over itself where it wraps a valve or a pump without overheating. That makes it the usual choice for freeze protection here. The specifications we read this year called for self-regulating cable at 5 watts per foot or left the type open, and the cable we installed was self-regulating.
Constant-wattage cable puts out the same heat along its whole length whether the pipe is cold or not. It must not overlap itself, and it needs a controller to keep it from running hot. It suits long, uniform runs where an engineer designs each circuit. On a roof or a plant skid, with valves, pumps and short branches, we rarely see it specified. We have installed it once in recent years, on a job in Lockhart, and everything since has been self-regulating.
Either way, ask for an ambient-sensing thermostat. One specification we priced turned the cable on below 40°F, and another below 38°F. Without one, the cable can run all summer.
The build we install
- Self-regulating heat trace, run along the lower side of the pipe under the insulation.
- Riser. Where the line leaves the roof it is exposed to wind first, so the trace starts at the roof.
- Valves and flanges. Extra cable is looped around the body, because a valve loses heat faster than straight pipe.
- Dead leg. An idle branch gets its own run of cable, out to the cap.
- Pump casing. The cable is wrapped around the pump, then the pump is insulated with the line.
- Power connection kit and ambient thermostat, in a weather-rated box, so the cable runs only when it is cold.
- End seal at the far end of each run of cable.
Our steps are the same on most jobs:
- Pressure test first, so nobody cuts insulation later to find a leak.
- Fasten the cable straight along the lower side of the pipe with glass tape about every foot. On plastic pipe and flat steel, aluminum tape over the cable spreads the heat. On the screening unit, the quote called for aluminum tape, then 2 inch rigid fiberglass and an aluminum jacket.
- Test the cable before insulating. One specification required it, and it is good practice everywhere.
- Insulate and jacket at the thickness the specification and energy code call for, sized to fit over the pipe and the cable.
- Test again once the system is closed up.
On the Austin office roof, the crew traced the 6 inch chilled-water piping at a rooftop pump, wrapped the cable around the pump, and spliced it into the existing heat trace with a splice kit so the circuit continued. They insulated the piping and pump with 1 inch elastomeric, plus about 4 feet of 1-1/2 inch phenolic with a metal jacket. Two days later one crew member came back and tested both the existing circuit at its power feed and the new extension, since the splice tied into a kit we had installed years earlier, and checked every connection in the splice.
Who handles the power
Specs often split this unclearly. One set this year had the electrician bringing four 208 volt circuits to a heat-trace controller, but did not say who furnished the cable. We coordinate it and settle the split in writing before the quote.
What drives schedule and price
- Footage by size, and the count of valves, flanges and pumps. Each fitting takes extra cable and extra labor.
- Cable lead time. On one package plant our crew waited several days for cable. Order it with the job, not after the crew is on site.
- Who buys the cable. Some vendors and contractors supply it and want labor only. On one Brenham-area unit the customer furnished the 120 volt, 5 watt self-regulating cable and our crew installed it. We split labor and material routinely.
- Existing systems. Splicing into an existing circuit on a roof takes care at the splice and a test of the whole circuit afterward, often on a second trip.
- The insulation system. Elastomeric, fiberglass with a PVC jacket, or phenolic with an aluminum jacket each price differently.
What to send for a quick quote
- The roof plan or yard layout with line sizes, or a marked-up drawing with lengths
- Which lines the specification says to trace, and the cable type and wattage if it names one
- Where power is, and whether you want us to bring the electrician
- The insulation and jacket the specification calls for
- Whether any existing heat trace has to be spliced or tested
- The date you need it working
Frequently asked questions
Does chilled-water piping need heat trace in Central Texas?
Outdoor and rooftop chilled-water piping often does, because the chiller may be off in winter and still water in an exposed line can freeze. Several jobs we priced this year traced it. Follow the drawings, and ask your insulation contractor to flag any exposed line left untraced.
Can heat trace go under the insulation on any pipe?
Yes, that is where it belongs. The cable runs along the pipe, and the insulation is sized to fit over both. On plastic pipe, aluminum tape over the cable helps spread the heat. If anyone changes the insulation thickness, tell whoever sized the cable first.
Does the insulation contractor do the electrical for heat trace?
We coordinate it. We install the cable with its connection and end-seal kits, and the power connections are made by the project electrician or by an electrical contractor we have worked with for the last decade. The split is settled before the quote, so nothing falls between trades.
Written by Chris Kelley from Bilt Rite Insulation's 2026 heat-trace work on rooftops, package plants and process equipment. Field detail from Ruben Zamora, BRI superintendent.